Identifying the Causes of Hidden Costs in Construction Projects: A Qualitative Study from the Perspective of Project Managers
Abstract
Hidden costs in construction projects represent a critical yet underexplored dimension of cost management. Unlike visible cost overruns, hidden costs are not directly traceable to specific budget lines, making them difficult to identify and control. This study aims to identify and classify the causes of hidden costs in construction projects from the perspective of project managers. Adopting a qualitative exploratory approach, semi-structured interviews were conducted with 13 experienced project managers, site managers, and project control experts in Tonekabon, Iran. Through thematic analysis, 72 initial codes were extracted and organized into 18 sub-themes and 6 main themes. The findings reveal that hidden costs emerge from six interrelated domains: managerial factors (weak planning and control, delayed decision-making, poor stakeholder coordination), technical and design factors (incomplete drawings, design changes, inaccurate estimation), execution-related factors (rework, poor quality, reduced productivity), financial factors (payment delays, increased indirect costs, weak cost control), contractual factors (ambiguities, changes and claims, disputes), and resource and supply factors (supply disruptions, resource waste, price volatility). The study demonstrates that hidden costs are not caused by isolated factors but rather emerge through the interaction and transfer of effects across multiple project phases. The paper concludes with practical recommendations for project managers, including implementing cause-tracking cost control systems, strengthening pre-construction coordination, and formalizing change management processes.
Keywords:
Hidden costs, Construction projects, Project management, Cost management, Cost overrun, Rework.References
- [1] Kermanshachi, S., Nipa, T. J., & Dao, B. (2023). Development of complexity management strategies for construction projects. Journal of Engineering, Design and Technology, 21(6), 1633–1657. https://doi.org/10.1108/JEDT-06-2021-0324
- [2] Elserougy, M., Khodeir, L. M., & Fathy, F. (2024). Practices and techniques for construction projects cost control-a critical review. HBRC Journal, 20(1), 525–552. https://doi.org/10.1080/16874048.2024.2337060
- [3] Okika, M. C., Vermeulen, A., & Pretorius, J. H. C. (2024). A systematic approach to identify and manage interface risks between project stakeholders in construction projects. CivilEng, 5(1), 89–118. https://doi.org/10.3390/civileng5010005
- [4] Afana, O., Al Zubaidi, R., Dabous, S. A., & Ibrahim, F. (2024). Categories and factors of cost overrun in construction projects: A systematic review. Engineering, Technology & Applied Science Research, 14(6), 18330–18347. https://doi.org/10.48084/etasr.9006
- [5] Abdelalim, A. M., Salem, M., Salem, M., Al-Adwani, M., & Tantawy, M. (2024). An analysis of factors contributing to cost overruns in the global construction industry. Buildings, 15(1), 18. https://doi.org/10.3390/buildings15010018
- [6] Tang, Y., & Yao, H. (2023). Watch out for the hidden costs of subcontracting in construction projects: The impacts of subcontractor dispersion. Journal of Construction Engineering and Management, 149(11), 4023113. https://doi.org/10.1061/JCEMD4.COENG-13307
- [7] Khadim, N., Thaheem, M. J., Ullah, F., & Mahmood, M. N. (2023). Quantifying the cost of quality in construction projects: An insight into the base of the iceberg. Quality & Quantity, 57(6), 5403–5429. https://doi.org/10.1007/s11135-022-01574-8
- [8] National Academies of Sciences. (2025). Open-book pricing practices for construction manager/general contractor and progressive design-build projects. https://www.nationalacademies.org/read/29084/chapter/4#8
- [9] Chen, L., Xu, C., Lim, W. H., Sharma, A., Tiang, S. S., Chong, K. S., …, & Khafaga, D. S. (2025). Transparent and reliable construction cost prediction using advanced machine learning and explainable AI. Engineering Science and Technology, an International Journal, 70, 102159. https://doi.org/10.1016/j.jestch.2025.102159
- [10] Ilka, O., & Rojhani, M. (2022). Cost Escalation as an Influential Factor in the Sustainable Management of Construction Projects in Iran (Causes of Cost Increases in Construction Projects). Amirkabir Journal of Civil Engineering, 54(2), 413–434. (In Persian). https://doi.org/10.22060/ceej.2021.18877.6989
- [11] Heinrich, J. (2026). Cost of rework in construction: Causes, data & prevention. https://www.planradar.com/us/cost-of-rework-construction/.
- [12] Love, P. E. D. (2026). Quantifying the costs of field rework in construction. Journal of Construction Engineering and Management, 152(1), 6025003. https://doi.org/10.1061/JCEMD4.COENG-17026
- [13] Gumusburun Ayalp, G., & Erdem, E. N. (2025). Unraveling the origins of construction rework: A holistic bibliometric analysis and exploration of causative factors. Open House International, 50(1), 65–97. https://doi.org/10.1108/OHI-10-2023-0235
- [14] Khahro, S. H., Shaikh, H. H., Zainun, N. Y., Sultan, B., & Khahro, Q. H. (2023). Delay in decision-making affecting construction projects: A sustainable decision-making model for mega projects. Sustainability, 15(7), 5872. https://doi.org/10.3390/su15075872
- [15] Muhaemin, A., & Suroso, A. (2025). Analysis of the influence of project communication management on owner decision to improve implementation time performance in high-rise building construction projects. ASTONJADRO, 14(2), 595–605. https://doi.org/10.32832/astonjadro.v14i2.17646
- [16] Kazar, G. (2025). A data-driven approach for predicting cash flow performance of public owners in building projects: Insights from Turkish cases. Engineering, Construction and Architectural Management, 32(11), 7507–7538. https://doi.org/10.1108/ECAM-06-2024-0706
- [17] Priyanka, A., & Pradyut, A. (2025). Navigating legal complexities in public infrastructure projects: The intersection of contract law and construction industry practices. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 17(3), 4525015. https://doi.org/10.1061/JLADAH.LADR-1284
- [18] Ding, M. J., & Jie, F. (2025). Mitigating the supply chain uncertainties and risks in the construction projects: Case studies of Australian construction projects. Cleaner Logistics and Supply Chain, 16, 100237. https://doi.org/10.1016/j.clscn.2025.100237
- [19] Guest, G., Bunce, A., & Johnson, L. (2006). How many interviews are enough? An experiment with data saturation and variability. Field methods, 18(1), 59–82. https://doi.org/10.1177/1525822x05279903
- [20] Nguyen, V. T., Do, S. T., Tran, C. N. N., & Van Pham, L. (2025). Analysis of interrelationships among constructs of cost overrun causes in consortium projects between construction contractors. International Journal of Construction Management, 25(13), 1596–1608. https://doi.org/10.1080/15623599.2025.2454366
- [21] Acharya, R., Yadav, M., & Thakur, V. (2026). Evaluating how effective project planning influences construction delays by examining planning quality, resource allocation and risk mitigation strategies. Engineering, Construction and Architectural Management, 1–26. https://doi.org/10.1108/ECAM-10-2025-1606
- [22] Ahmed, S., Alahmadi, Y. A., & Aman, M. (2026). Impact of cause and effect on project performance and mitigation management. International Journal of Information Technology Project Management (IJITPM), 17(1), 1-23. https://doi.org/10.4018/IJITPM.408169
- [23] Zhang, S., Yosia, S. R., Jinpeng, W., Zhenwen, S., Yongjian, K., & Xiaoping, L. (2025). The causation of design error in the construction industry: A multistakeholder perspective. Journal of Performance of Constructed Facilities, 39(1), 4024055.
- [24] Qing, L. Z., Mohd-Rahim, F. A., Mahdzir, M., Mustafa, M. H., & Alashwal, A. (2025). Design errors’ impact on construction project costs. Journal of Construction in Developing Countries, 30(2), 25–47. https://researchers.westernsydney.edu.au/files/384374520
- [25] Liannian, W., Joomyung, L., Jatin, N., Kevin, H., & Abhinav, G. (2024). Integrated 4D design change management model for construction projects. Journal of Construction Engineering and Management, 150(5), 4024023. https://doi.org/10.1061/JCEMD4.COENG-14246
- [26] Aljordi, S. H., Falah, M., & Soleimani, M. (2024). Identifying factors affecting accurate estimation of time and cost of construction project completion using factor analysis: A case study of commercial and residential buildings in Arak. Journal of Structural and Construction Engineering, 8(2). (In Persian). https://elmnet.ir/doc/2823663-17879
- [27] Asitha, R., Danny, M., & Campbell, M. (2024). Measuring activity-level construction productivity. Journal of Construction Engineering and Management, 150(8), 4024099. https://doi.org/10.1061/JCEMD4.COENG-14602
- [28] Nnadi, E. O. E., & Najjobyo, J. (2025). Financial and operational effects of cost estimation inaccuracy, material price volatility, and payment delays in Nigerian construction projects. Smart Construction and Sustainable Cities, 3(1), 29. https://doi.org/10.1007/s44268-025-00076-4
- [29] Alotaibi, R., Sohail, M., Edum-Fotwe, F. T., & Soetanto, R. (2026). Determining project control system effectiveness in construction project delivery. Engineering, Construction and Architectural Management, 33(5), 3682–3717. https://doi.org/10.1108/ECAM-04-2024-0529
- [30] Angmor, C. T., Tagoe, A., Anugwo, I. C., & Okorafor, C. (2026). Model for analysing supply chain disruptions and cost volatility in construction materials markets. International Journal of Construction Management, 1–16. https://doi.org/10.1080/15623599.2026.2643736