Risk Management in Road Construction Projects: A Fuzzy ANP Approach for Prioritizing Critical Factors

Authors

  • Nasser Pourgholam * Structural Supervisor, Construction Engineering Organization, Mazandaran Province, Iran.

https://doi.org/10.48314/jcase.vi.86

Abstract

Road construction projects are inherently associated with numerous risks and uncertainties that can significantly impact project objectives including cost, time, and quality. This paper presents a comprehensive risk assessment framework for road construction projects using fuzzy Analytic Network Process (ANP) methodology. A case study of road construction projects in Tonkabon city, Iran, is conducted to identify, evaluate, and prioritize risk factors affecting project performance. Through literature review and expert consultation, five main risk categories and ten sub-criteria were identified. The fuzzy ANP method was employed to handle the inherent uncertainty in expert judgments and capture interdependencies among risk factors. Results indicate that employer-related risks (weight: 0.27) rank first, followed by accident-related risks (0.23), machinery-related risks (0.18), contractor-related risks (0.16), and consultant-related risks (0.14). Among sub-criteria, lack of access to skilled and expert personnel emerged as the most critical risk factor (weight: 0.12). The findings provide valuable insights for project managers and stakeholders in developing proactive risk mitigation strategies for road construction projects. The proposed methodology offers a systematic approach for risk prioritization that can be adapted to various infrastructure project contexts.

Keywords:

Risk management, Uncertainty, Road construction, Fuzzy ANP, Employer, Contractor

References

  1. [1] Alamgir, M., Campbell, M. J., Sloan, S., Goosem, M., Clements, G. R., Mahmoud, M. I., & Laurance, W. F. (2017). Economic, socio-political and environmental risks of road development in the tropics. Current Biology, 27(20), R1130-R1140. https://doi.org/10.1016/j.cub.2017.08.067

  2. [2] Zayed, T., Amer, M., & Pan, J. (2008). Assessing risk and uncertainty inherent in Chinese highway projects using AHP. International Journal of Project Management, 26(4), 408–419. https://doi.org/10.1016/j.ijproman.2007.05.012

  3. [3] Perera, B., Rameezdeen, R., Chileshe, N., & Hosseini, M. R. (2014). Enhancing the effectiveness of risk management practices in Sri Lankan road construction projects: A Delphi approach. International Journal of Construction Management, 14(1), 1–14. https://doi.org/10.1080/15623599.2013.875271

  4. [4] Project Management Institute (PMI). (2017). A guide to the project management body of knowledge (PMBOK). https://tegnum.edu.pe/wp-content/uploads/2023/09

  5. [5] Azar, A., & Faraji, H. (2007). Fuzzy management science. Mehraban Book Publishing House. (In Persian). https://dl.iust.ac.ir/dl/search/default.aspx?Term=4237&Field=0&DTC=1

  6. [6] Rezaeian, J., & Iranian, M. (2018). Risk assessment in road construction projects based on the PMBOK standard case study: Cable bridge construction project the city of Sari. Journal of Passive Defense, 9(3), 55–66. (In Persian). https://pd.ihu.ac.ir/article_200762.html?lang=en

  7. [7] Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: A guide to measuring and monitoring project performance. John Wiley & Sons. https://doi.org/10.1002/9781119427599

  8. [8] Dixit, S., Sharma, K., & Singh, S. (2020). Identifying and analysing key factors associated with risks in construction projects. Emerging trends in civil engineering: Select proceedings of ICETCE 2018. (pp. 25–32) Springer. https://doi.org/10.1007/978-981-15-1404-3_3

  9. [9] El-Sayegh, S. M., & Mansour, M. H. (2015). Risk assessment and allocation in highway construction projects in the UAE. Journal of Management in Engineering, 31(6), 4015004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000365

  10. [10] Fathollahzadeh, S., & Mehdizadeh, R. (2013). Investigating the risks of road construction projects in iran as a developing country. International conference on civil engineering architecture & urban sustainable development, Tabriz, Iran. (In Persian). https://www.researchgate.net/publication/258395922

  11. [11] Perera, B., Dhanasinghe, I., & Rameezdeen, R. (2009). Risk management in road construction: The case of Sri Lanka. International Journal of Strategic Property Management, 13(2), 87–102. https://doi.org/10.3846/1648-715X.2009.13.87-102

  12. [12] Zou, P. X., Zhang, G., & Wang, J. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management, 25(6), 601–614. https://doi.org/10.1016/j.ijproman.2007.03.001

  13. [13] Taherian Amiri, M. J., Haghighi, F. R., Eshtehardian, E., Hemmatian, M., & Javaheri Barforoushi, M. (2020). Implementing the critical chain method for managing linear-repetitive projects such as road construction, taking into account the conditions of uncertainty and risk. Journal of Structural and Construction Engineering, 7(2), 60–74. https://doi.org/10.22065/jsce.2018.121553.1492

  14. [14] Odumade, A., Urokor, M., & Onyekweredike, K. (2020). Sustainable development and risk management in road construction industry in Nigeria. https://doi.org/10.22541/au.157971245.52458953

  15. [15] Ganapthy, V. R., Subramaniam, S. K., Diah, A. B. M., Suaidi, M. K., & Hamidon, A. H. (2010). Flagman and risk involved in road construction site. International Journal of Sustainable Construction Engineering and Technology, 1(1), 113–118. https://publisher.uthm.edu.my/ojs/index.php/IJSCET/article/download/55/14

  16. [16] Thomas, A. V, Kalidindi, S. N., & Ganesh, L. S. (2006). Modelling and assessment of critical risks in BOT road projects. Construction Management and Economics, 24(4), 407–424. https://doi.org/10.1080/01446190500435275

  17. [17] Alam, S., Yin, Z., Ali, A., Ali, S., Noor, A., & Jan, N. (2019). A comprehensive study of project risks in road transportation networks under CPEC. International Journal of Financial Studies, 7(3), 41. https://doi.org/10.3390/ijfs7030041

  18. [18] Moradpour, S., Ebrahimnejad, S., Mehdizadeh, E., & Mohamadi, A. (2011). Using hybrid fuzzy PROMETHEE II and fuzzy binary goal programming for risk ranking: A case study of highway construction projects. Journal of Industrial Engineering, 5(3), 47–55. https://www.sid.ir/paper/620780/en

  19. [19] Saaty, R. W. (2003). Decision making in complex environment: The analytic hierarchy process (AHP) for decision making and the analytic network process (ANP) for decision making with dependence and feedback. Pittsburgh: Super Decisions. http://iors.ir/journal/files/site1/user_files_ba3acb/mehdi_ghotboddini-A-10-6-2-f082faa.pdf

  20. [20] Wu, W. W., & Lee, Y. T. (2007). Selecting knowledge management strategies by using the analytic network process. Expert Systems with Applications, 32(3), 841–847. https://doi.org/10.1016/j.eswa.2006.01.029

  21. [21] Sohrabinejad, A., & Rahimi, M. (2015). Risk determination, prioritization, and classifying in construction project case study: Gharb Tehran commercial-administrative complex. Journal of Construction Engineering, 2015(1), 203468. https://doi.org/10.1155/2015/203468

  22. [22] Guo, J., Xiang, P., & Lee, Y. (2022). Analyzing and controlling construction engineering project gray rhino risks with innovative mcdm methods: Interference fuzzy analytical network process and decision-making trial and evaluation laboratory. Applied Sciences, 12(11), 5693. https://doi.org/10.3390/app12115693

  23. [23] Jafarian, M. R., Ardeshir, A., & Boyaghchi Firouzi, A. (2022). Designing a financial risk assessment model for public-private partnership financing for road construction projects in Iran. Journal of Structural and Construction Engineering, 2(5), 65–95. https://doi.org/10.22065/jsce.2020.197498.1925

  24. [24] Mohajeri Borj Qaleh, R., Pourrostam, T., Mansour Shariflou, N., Majrouhi Sardroud, J., & Safa, E. (2020). Reviewing causes of delay from the risk management perspective in execution stage in road construction projects (Case study: Garmsar-Simin Dasht road). Journal of Civil Infrastructure Research, 5(2), 69–82. https://doi.org/10.22091/cer.2020.5274.1196

  25. [25] Rezaee Arjroody, A., Hosseini, S. A., Akhbari, M., Safa, E., & Asadpour, J. (2023). Identification and prioritization of road project risks using the failure modes and effects analysis method in a fuzzy environment. International Journal of Transportation Engineering, 11(2), 1443–1455. https://www.ijte.ir/&url=http:/www.ijte.ir/article_170321_f9e9cdad857fb7acbc2299a7f3d85976.pdf

  26. [26] Lawshe, C. H. (1975). A quantitative approach to content validity. Personnel Psychology, 28(4), 563. https://doi.org/10.1111/j.1744-6570.1975.tb01393.x

  27. [27] Cronbach, L. J. (1951). Coefficient alpha and the internal structure of tests. Psychometrika, 16(3), 297–334. https://doi.org/10.1007/BF02310555

  28. [28] Buckley, J. J. (1985). Fuzzy hierarchical analysis. Fuzzy Sets and Systems, 17(3), 233–247. https://doi.org/10.1016/0165-0114(85)90090-9

  29. [29] Dubois, D., & Prade, H. (1980). Fuzzy sets and systems: Theory and applications. Academic press. https://doi.org/10.2307/2273604

Published

2026-10-05

How to Cite

Pourgholam, N. (2026). Risk Management in Road Construction Projects: A Fuzzy ANP Approach for Prioritizing Critical Factors. Journal of Civil Aspects and Structural Engineering, 3(4), 237-248. https://doi.org/10.48314/jcase.vi.86

Similar Articles

1-10 of 44

You may also start an advanced similarity search for this article.